Walla Walla High School Renovation
Tentative Project Schedule/Phasing Plan
- New Science Building: Oct 19 - Aug 20
- Site Utilities Improvements: March 20 - Sep 21
- Old Science Building Renovation, Music Building Addition, Fitness Addition: Sep 20 - Aug 21
- Commons Improvements, Media Center Improvements/Culinary Addition: Dec 20 - Fall 21
- Academic Building Renovation: June 21-Aug 22
- CTE Building/Greenhouse Improvements and Site/Parking Closeout: December 21-August 22
Performing Arts Expansion Live Construction Site Feed
- Time-Lapse Construction Video
- Live Construction Camera (click on menu below and select live video)
Commons and Culinary Arts Live Feed Construction Camera
- Time-lapse Construction Video
- Live Construction Camera (click on menu below and select live video)
Design Updates
- Preliminary Construction Document Exterior Renderings and "Fly-over" Animation (2/2020)
- Design Development Floorplans and Renderings (10/1/19)
- Overall Site Plan
- "Typical" Classroom Layout
- Building 1 (Vo-Ag)
- Building 2 ("Old Science Building")
- Building 3 (Commons)
- Building 4 (Library/CTE Expansion)
- Building 5 ("Academic/Main Building")
- Building 6 (Gym Complex)
- Building 7 (Performing Arts)
- Exterior Renderings
Schematic Design 3-D Modeling
- WaHi Abbott Road View of Academic Building and Office