Walla Walla High School Renovation
Tentative Project Schedule/Phasing Plan
- New Science Building: Oct 19 - Aug 20
- Site Utilities Improvements: March 20 - Sep 21
- Old Science Building Renovation, Music Building Addition, Fitness Addition: Sep 20 - Aug 21
- Commons Improvements, Media Center Improvements/Culinary Addition: Dec 20 - Fall 21
- Academic Building Renovation: June 21-Aug 22
- CTE Building/Greenhouse Improvements and Site/Parking Closeout: December 21-August 22
Wa-Hi Academic, South, Construction Time-Lapse Videos
No longer available.
Design Updates
Exterior Renderings
Schematic Design 3-D Modeling
WaHi Abbott Road View of Academic Building and Office