Green light for Pioneer roof project

The Walla Walla Public Schools Board of Directors during a special meeting today unanimously approved the bid of $246,890 from D&D Roofing & Construction of Puyallup, WA for the Pioneer Middle School roof replacement project. The total cost of the project, including 8.9 percent sales tax, is $268,863.21. The project will begin soon and be completed by August 27. Directors Ruth Ladderud and Dr. David Hampson were absent from today’s meeting.

Facilities Support Director Dan Johnson reported D&D Roofing & Construction was the low bidder of the four companies vying for the project. He said state law requires the district to select the low bid if it meets the specified requirements of the project. Johnson reported D&D Roofing & Construction met the bid requirements. The project includes removing existing roofing materials to the roof deck for the entire school, including the gym, and replacing underlayment, membrane and asphalt shingles.

Bids by the numbers:

D&D Roofing & Construction (Puyallup, WA): $246,890

Elsom Roofing (College Place, WA): $270,500

Royal Roofing (Pasco, WA): 284,270

Gillespie Roofing (Walla Walla, WA): $326,465

 